Items required in the field for Inspection:
- Approved site plan
- Solar plans, these will not have a building dept stamp on them.
- Job card
- Permit
- 10 kw or less Check list
Steps:
- Look for all items mentioned above
- Check for no electrical in CWP structures, (if any)
- Make sure everything is according to the plan and all items on the check list are marked yes. If all is correct you can final this permit.
- If there are any discrepancies from the plan to the field, then a correction notice will be required.
- The check list only applies to 10kw or less it is not required for 10kw or more.
- Do not write a correction for a checklist if the plans are approved and the system is over 10kw