Schedule the following inspections:
- Ground electrode
- Rough electric
- Grounding and bonding
- Service panel
- Final inspection ( This is a on-time inspection, any other added inspections or corrections will result in additional fees)
Requirements:
- Must have approved site plan identifying well and pump location, main panel location and disconnect location.
- Site plan must show location of proposed crop location.
- Permit, job card and approved electric to well single line stamped by County of Riverside must be on site.
- All electrical must be complete and exposed for inspection.
- All grounding and bonding must be complete, well casing if metal, ground rods and metal boxes.
- All conduit from service to disconnect and pump must be in place, if buried then potholes at both ends and 50’ intervals will be fine to verify burial depth.
- All irrigation must be in place up to the location of the proposed crops.
- These are 100 A max busbar rating, read label to verify, must be rated for outdoor use.
- This will be allowed to have the main breaker and the disconnect breaker only, there are no other circuits allowed to be attached. No breakers, no outlets. No exceptions.